BMS Car Deployment 2
Update 5/2/2026 (See Below)
I built up and mounted four more BMS units in CINCH and Jameco enclosures. See the blog (BMS Ready for Deployment) to review the reason for the Jameco enclosures. These are to be installed in the rear seat with the batteries there. The CAN BUS data and power cables have been made. Still working on the temperature measurement cables. All of the enclosures will be attached to the deck of the rear seat. Unfortunately because of where the BMS units will be mounted in the rear seat all four of the DB25 cables on the batteries will need an extension cable.

Before deploying the BMS units I tested each of them with a program that tests the functionality of the BMS. It logs the 10 voltages measured by the BMS every 5 seconds and runs for 12 hours or more. For this test, code was developed to read the CAN BUS data from the BMS unit and send that out on the USB as serial data. It works very similar to my BMS Reader system, except only one BMS is under test and the data is sent out on the serial bus as text instead of writing to the SD card. The serial data is the HEX CAN BUS frame received from the BMS, converted into text. The HEX data is sent as text on the serial bus. The test program converts the HEX text data to digital and that is what is displayed in the screen shot of the LabView test code below with a GUI that shows the voltage of each cell as a graph. In the screen shot below the box highlighted in red is what one frame of CAN BUS data looks like as HEX data. The first number in the frame (0x61) is the frame number and the second number is the number of bytes in the frame (0x8). Each pair of bytes represent one voltage measurement. Since there are 8 bytes in a frame, four cell voltage measurements are represented in the frame. The first cell HEX data 0x77B1 is 30641 decimal, which when divided by 10,000 gives the cell voltage value. Four CAN BUS frames are required for all the BMS data. The first three frames are the voltage measurements and the fourth frame are the temperature measurements.

The voltages are created by a benchtop power supply and a resistor ladder. See image below. Each resistor is a precision 1K ohm resistor and 10 are are wired in series on the barrier strip to simulate the ten cells in the battery. Nearly the exact same voltage is dropped across each resistor. The difference in the cell readings shown in the screen shot above is do to the resistor precision. You can see from the screen shot that the Std Dev is less that 1mV and that is the variation of all 10 cells combined. This is the same method I used to test my BMS boards against the DC6620A BMS demo board (see BMS Bench Testing blog). For this testing, the CINCH enclosure labeled CAN BUS Reader is just a BMS PCA that has the Arduino Nano Every USB connected to the USB feedthrough so that the serial CAN BUS data could be read by the computer, running the LabView test program. I found looking at the BMS measurement variance in the 12 hour data that the benchtop power supply had more variation than any one BMS cell on any BMS unit. The tests showed all BMS units working very well and the measurements for any channel were very consistent.

Next steps are to finish all the cabling and mount the BMS units on the rear seat batteries. I will have to use a right-angle DB25 connector like the one shown below to connect to the batteries to give the battery cables a low profile to fit under the rear seat cushion. Link to this part.
I will also use these same 12mm tee connectors with the BMS units for the rear seat batteries, as I had for the trunk battery BMS units.
Here is the link for part number T58-A04-FMFR001 catalog page.

Update 5/2/2026
Below is what the layout of BMS units for the rear seat batteries looks like. The middle two Jameco enclosures will be further apart than shown in this image, which is why the data cable between them is longer. Before I can mount these in the rear seat I need to remove the rear seatbelt mounts. No one is going to sit in the rear seat now and the seatbelt mounts are bolted to the seat deck, in the same place the BMS units need to go. I will not need a separate mounting rail like I used in the trunk battery box. I can attach the BMS units directly to the metal of the seat deck. Before I do that I am going to mount some sound proofing underlament like I used under all the carpeting.

All of the DB25 extension cables for the battery connections have been assembled and tested. All of the temperature sensor cables have been assembled, but still need to attach the temperature sensor to those cables. I am using the same 1-wire sensors in a TO-92 case (link) that I used for the trunk box batteries. I found the heatsinks below (link) to mount the temperature sensors in to make good thermal contact to the battery case. They are small enough to slide between the batteries. Shown below the heatsink is how I electrically connected the sensors, using screw terminals with wires soldered to the pins. I will use some silver epoxy with the heatsinks to ensure good thermal contact to the 1-wire sensors.